Pielstick Engine Major Overhaul

by | Dec 12, 2025 | CASE STUDY

A 12,000 running hours major overhaul was carried out by INJEGOV on a Pielstick medium-speed diesel engine operating in a power generation plant. The scope of work covered complete engine disassembly, detailed inspection, component reconditioning, precision measurements, reassembly, and commissioning, ensuring compliance with OEM standards and stable operation under continuous load.

Project Type 

12,000 Running Hours Major Overhaul
Engine Type: Pielstick (MAN / SEMT Pielstick)
Application: Power Generation – Medium-Speed Diesel Engine

Overview

INJEGOV successfully carried out a 12,000 running hours major overhaul on a Pielstick medium-speed diesel engine, following the manufacturer’s maintenance schedule and OEM technical guidelines.

The project included full disassembly, inspection, reconditioning, reassembly, testing, and commissioning, restoring the engine to optimal operational condition and ensuring long-term reliability under continuous load.

This overhaul formed part of a planned preventive maintenance program, designed to maximize engine lifespan, maintain performance efficiency, and minimize the risk of unplanned downtime.

Cylinder Heads & Valve Mechanism Overhaul

  • Complete removal and refitting of all cylinder heads|
  • Full disassembly, cleaning, and inspection of components
  • Hydraulic pressure testing and non-destructive testing (dye penetration)
  • Reconditioning of exhaust and inlet valves, valve seats, and guides
  • Replacement of worn valve bodies, sealing rings, and rotocaps
  • Machining and restoration of gasket and sealing surfaces
  • Rocking gear inspection and reconditioning
  • Final tappet clearance adjustment according to OEM specifications

Fuel Injection System Overhaul

  • Removal and refitting of injectors and injection pipes
  • Injector calibration, atomization, and tightness testing
  • Reconditioning and inspection of fuel injection pumps
  • Timing adjustment using calibrated shims
  • Final synchronization to ensure uniform peak cylinder pressures

Pistons, Liners & Connecting Rods

  • Extraction and inspection of all cylinder liners
  • Dimensional measurement, ovalization checks, and dye penetration testing
  • Honing of liners to restore surface finish
  • Repair of liner cooling grooves where cracks were identified
  • Complete piston overhaul including:
    – Cleaning and inspection of piston crowns and skirt
    Measurement and restoration of piston grooves
    – Replacement of piston rings
    – Clearance verification before and after reconditioning
    • Connecting rod inspection, MPI testing, and bearing shell replacement
    • Verification of clearances between crankpin and connecting rod shells

    Crankshaft, Bearings & Crankcase

    Two heat exchange systems were serviced during the project:

    • Main Engine L.O. Cooler (183 plates) — cleaned chemically in situ via recirculation

    • Auxiliary Condenser — mechanically cleaned, inspected, and reassembled with new gaskets

    Both systems were restored to maximum cooling efficiency and operational reliability.

    Timing Gear & Auxiliary Systems

    • Inspection of cams, tappets, rollers, and push rods
    • Timing gear backlash measurements and verification
    • Replacement of oil seals and worn sleeves
    • Overhaul of lubrication, fuel oil, fresh water, and starting air systems
    • Overhaul and hydraulic testing of air coolers
    • Cleaning of cooling jackets and sump tank

    Quality Control & Testing

    A comprehensive quality assurance and testing process was applied throughout the overhaul, including detailed dimensional measurements recorded before and after reconditioning, non-destructive testing (NDT) on critical components, hydraulic and leak testing of cylinder heads and liners, and verification of all mechanical clearances against OEM tolerance limits, ensuring full compliance with manufacturer specifications and reliable operation in a power plant environment.

    Engine Trials & Commissioning

    After reassembly, the engine underwent:

    • Controlled running-in procedure
    • Load trials at 14.4 MW and 17 MW
    • Fine tuning of fuel injection timing to balance Pmax values
    • Endurance operation to confirm mechanical stability and performance

    Results of the 12,000h Pielstick Engine Overhaul

    • Full restoration of engine performance after 12,000 running hours

    • Critical components returned to OEM specifications

    • Improved reliability and operational stability

    • Extended service life and reduced risk of unplanned failures

    Engine delivered back to operation ready for continuous duty

    INJEGOV Expertise in Pielstick Engine Overhauls

    This project highlights INJEGOV’s proven capability in executing large-scale Pielstick engine overhauls, including:

    • OEM-compliant overhaul procedures
    • Advanced mechanical reconditioning
    • Precision measurements and documentation
    • In-depth expertise in medium-speed diesel engines
    • Reliable execution within planned maintenance schedules

    INJEGOV provides complete overhaul solutions for Pielstick engines used in power generation, marine, and industrial applications.

    Read more

    Learn the latest Injegov News, including information on our company’s latest investments, innovations and corporate social responsibility acts.

    Dec 29 2025

    Shanghai Mechanical Workshop

    INJEGOV SA announces the opening of its new Mechanical Workshop in Shanghai, expanding technical services and spare...
    2025 retrospect
    Dec 16 2025

    2025 Retrospect

    A look back at 2025: strategic expansions, technical excellence, and strong partnerships that drove INJEGOV’s growth...
    Dec 16 2025

    On-Site Crankshaft Grinding: Reduce Downtime & Costs

    On-site crankshaft grinding restores damaged journals to OEM tolerances without crankshaft removal, reducing downtime,...
    Dec 16 2025

    INJEGOV SA Receives ESG Rating Certificate

    INJEGOV SA has received an ESG Rating B through the Synesgy platform by ICAP CRIF, confirming a moderate–high level of...
    Dec 11 2025

    Understanding FIVA Valves & Their Impact on ME Engine Performance

    FIVA valves play a critical role in fuel injection and exhaust timing on ME engines. This insight explains how they...
    Nov 27 2025

    Workshop Upgrades with FIVA Test Bench and Specialized Training

    INJEGOV has upgraded its workshop with a state-of-the-art test bench for FIVA, ELFI, and ELVA valves, enabling highly...
    Nov 27 2025

    Four-Stroke Crankshaft Reconditioning with Laser Cladding

    This project showcases the complete reconditioning of a four-stroke crankshaft at INJEGOV’s mechanical workshop in...
    Nov 17 2025

    Woodward UG-10 Governor

    A high-output mechanical-hydraulic governor delivering precise, stable speed control for diesel/gas engines and steam...
    INJEGOV Renews GALI Authorized Distributor Agreement for 2026
    Nov 13 2025

    INJEGOV Renews GALI Partnership for 2026

    INJEGOV welcomed GALI’s Branch Director, Enrico Borando, to its headquarters in Greece for the official signing of the...
    Nov 03 2025

    INJEGOV Appointed GEISLINGER Authorized Distributor for Cyprus and Israel

    After two years of successful collaboration in Greece as an official Sales and Service Partner, INJEGOV S.A. has been...