HIMSEN 6H21/32 auxiliary engine overhaul including cylinder heads, pistons, fuel pumps and deflection measurements, carried out by INJEGOV’s expert engineers with workshop support to ensure stable operation and reliable generator performance.

HIMSEN 6H21/32 Auxiliary Engine Overhaul

In this project, INJEGOV carried out a complete HIMSEN 6H21/32 auxiliary engine overhaul, including dismantling, inspection, calibration and reassembly of critical components, in full compliance with OEM specifications and operational requirements.

This HIMSEN 6H21/32 auxiliary engine overhaul was carried out combining onboard execution and workshop reconditioning, ensuring proper generator performance and operational reliability.

INJEGOV successfully completed a full-scope overhaul and reconditioning project for a GE-HIMSEN 8H25/33 auxiliary engine, restoring operational reliability, extending component lifespan, and ensuring compliance with OEM standards.

Scope of Work

After dismantling all major components, including cylinder heads, pistons with connecting rods, and fuel pumps, all parts were transferred to the workshop for cleaning, calibration, and inspection.

Cylinder heads were fully stripped from valves and fittings, cleaned and checked by dye penetration, followed by hydraulic pressure testing and reassembly with new spare parts.

Pistons and connecting rods were dismantled and inspected, including pins, bushes, liners, and grooves, followed by calibration and reassembly with new piston rings.

Fuel pumps were overhauled, calibrated, and reassembled, including adjustment of fuel timing.

Crankshaft deflection measurements were carried out before and after the overhaul to verify proper alignment and operational condition.

HIMSEN 6H21/32 Overhaul Works Performed

HIMSEN 6H21/32 Cylinder Head Overhaul

The HIMSEN 6H21/32 cylinder head overhaul included full dismantling, inspection and reconditioning of components.

  • Dismantling of cylinder heads
  • Removal of all attached components (rocker arms, injectors, valves)
  • Cleaning and calibration
  • Dye penetration inspection
  • Hydraulic pressure testing
  • Reassembly and installation

HIMSEN 6H21/32 Piston & Connecting Rod Overhaul

The HIMSEN 6H21/32 piston and connecting rod overhaul included complete dismantling, inspection and calibration of all piston assemblies.

    • Dismantling of pistons with connecting rods
    • Cleaning and dimensional calibration
    • Inspection of pins, bushes, liners and grooves
    • Dye penetration inspection
    • Reassembly with new piston rings 

HIMSEN 6H21/32 Fuel Pump Overhaul

The HIMSEN 6H21/32 fuel pump overhaul ensured proper fuel injection and engine performance.

    • Dismantling of high-pressure fuel pumps
    • Cleaning and calibration
    • Renewal of worn components
    • Reassembly and installation
    • Adjustment of fuel timing

Deflection Measurement

As part of the HIMSEN 6H21/32 auxiliary engine overhaul, crankshaft deflection measurements were carried out to verify alignment and mechanical condition.

  • Measurement before overhaul
  • Measurement after overhaul
  • Recording and evaluation of values

All measurements were within acceptable operational limits.

Quality Control & Testing

All stages of the HIMSEN 6H21/32 auxiliary engine overhaul were carried out under strict quality control procedures.

  • Dye penetration testing (NDT)
  • Hydraulic pressure testing
  • Dimensional calibration
  • Clearance measurements and reporting

All measurements were recorded and evaluated within acceptable operational limits.

Results of the HIMSEN 6H21/32 Auxiliary Engine Overhaul

The completion of the HIMSEN 6H21/32 auxiliary engine overhaul ensured restored engine condition and reliable operation.

✔ Stable generator performance
✔ Improved combustion and fuel efficiency
✔ Verified alignment and clearances
✔ Reduced mechanical wear
✔ Reliable and continuous operation

Read more

Learn the latest Injegov News, including information on our company’s latest investments, innovations and corporate social responsibility acts.

CERTIFIED SERVICE PARTNER
Apr 23 2026

HD Hyundai Marine Solution Tech Certified Service Partner

INJEGOV SA has been officially appointed as a Certified Service Partner within the HD Hyundai Marine Solution Tech...
Apr 23 2026

INJEGOV Training at HD Hyundai Marine Solution Tech Headquarters in Busan, South Korea

INJEGOV SA’s mechanical engineers from INJEGOV Greece and INJEGOV Turkey attended official specialized training at HD...
Apr 17 2026

Main & Auxiliary Engine Overhaul MAN B&W 6S50MC-C & HIMSEN 6H21/32

Complete main & auxiliary engine overhaul including MAN B&W 6S50MC-C and HIMSEN 6H21/32 engines, covering...
Apr 17 2026

MAN B&W 6S50MC-C Main Engine Overhaul

Complete MAN B&W 6S50MC-C main engine overhaul including dismantling, detailed inspection, piston and cylinder...
Apr 02 2026

On-Site Crankshaft Grinding on Daihatsu DK-28 8-Cylinder Engine

A technical overview of on-site crankshaft grinding on a Daihatsu DK-28 8-cylinder medium-speed diesel engine,...
Apr 02 2026

GE-HIMSEN 8H25/33 Engine Overhaul

E-HIMSEN 8H25/33 engine overhaul, delivering OEM-standard reconditioning, precision machining and reliable performance...
Mar 31 2026

Governor Services in China

INJEGOV provides expert governor services in China, including overhaul, repairs, reconditioning and spare parts...
Hyundai HiMSEN 8H32/40 Cylinder covers during assemply with new parts (2)
Feb 03 2026

Hyundai HiMSEN 8H32/40 Auxiliary Engine overhaul

INJEGOV completed a full workshop overhaul of a Hyundai HiMSEN 8H32/40 auxiliary engine, restoring critical combustion...
Feb 02 2026

INJEGOV sponsors MARTECMA 2026 New Year’s Dinner

INJEGOV SA was honored to participate as a Gold Sponsor at the MARTECMA New Year’s Dinner, held at the iconic Hotel...
Feb 02 2026

CIMAC Membership

INJEGOV SA, as an independent manufacturer, supplier, and service provider operating within the marine diesel engine...